Considering the time required by prime contractors to reactivate (actually
to recreate) product lines, install manufacturing equipment plus
acquisition of materials, parachute hardware, manufacturing tools and
skills; acquire components through outsource or in-house-manufacture,
and lead time to integrate production and assembly, and ship complete
parachutes, etc., was much too long. It got down to how many of each
type parachute (seat, back or chest) was most urgently needed, and how
could we get the right types and number of parachutes to where they had
to be. What was the mix of parachute types to be procured
commercially, checked through the USAF internal quality assurance
process, and shipped (packed or unpacked based on circumstances) to
meet Korean Theater needs in a combat environment and rapid changes
in the Theater's types of aircraft?
A 'complete' parachute, as procured during WW2 consisted of all of its
components assembled and permanently connected to each other, except
for the pilot parachute, ripcord, and 6 bungee/hook assemblies, all of
which were installed by the rigger during the pack-for-service process.